    Question

    Why should test data prepared during the implementation

    phase of a program be preserved in information system?
    A To provide a frame of reference for future audits and verify program integrity Correct Answer Incorrect Answer
    B To avoid rewriting code during audits Correct Answer Incorrect Answer
    C To ensure the program runs faster in the future Correct Answer Incorrect Answer
    D To train end-users on how to use the program Correct Answer Incorrect Answer

    Solution

    The correct answer is A