📢 Too many exams? Don’t know which one suits you best? Book Your Free Expert 👉 call Now!


    Question

    A company recognises revenue over time for a contract.

    Costs incurred to date = ₹40,00,000; total estimated cost = ₹1,00,00,000; total contract price ₹1,40,00,000. Revenue recognised to date = ? (cost-to-cost method)
    A ₹56,00,000 Correct Answer Incorrect Answer
    B ₹40,00,000 Correct Answer Incorrect Answer
    C ₹64,00,000 Correct Answer Incorrect Answer
    D ₹1,40,00,000 Correct Answer Incorrect Answer

    Solution

    Percentage of Completion = (Costs Incurred to Date / Total Estimated Costs) = 40,00,000 / 1,00,00,000 = 40%. Revenue to be Recognized = Total Contract Price × Percentage of Completion = 1,40,00,000 × 40% = ₹56,00,000.

    Practice Next
    ask-question