      A budget that is prepared based on a single level of

      activity is known as a:
      A Flexible Budget Correct Answer Incorrect Answer
      B Static Budget Correct Answer Incorrect Answer
      C Rolling Budget Correct Answer Incorrect Answer
      D Cash Budget Correct Answer Incorrect Answer
      E Master Budget Correct Answer Incorrect Answer

      Solution

      A Static Budget, also known as a Fixed Budget, is prepared for a single, planned level of activity. It does not change with actual changes in activity levels. A Flexible Budget (A), in contrast, is designed to change with the volume of activity.