Question

When is revenue from construction contract recognised under Ind AS when outcome cannot be estimated reliably?

A Recognise contract revenue to the extent of contract costs incurred that are expected to be recoverable; recognise expected losses immediately
B Recognise full contract revenue upfront
C Defer all revenue until completion
D Recognise as non-current liability
E Recognise as OCI only