    A company enters into a contract to construct a

    specialized asset over 4 years. At the end of Year 2, total costs incurred are ₹60 lakh, estimated total costs are ₹100 lakh, and total contract revenue is ₹130 lakh. Which amount should be recognized as revenue till Year 2 under AS 7?
    A ₹60 lakh Correct Answer Incorrect Answer
    B ₹78 lakh Correct Answer Incorrect Answer
    C ₹65 lakh Correct Answer Incorrect Answer
    D ₹70 lakh Correct Answer Incorrect Answer
    E ₹75 lakh Correct Answer Incorrect Answer

    Solution

    Revenue recognized = (Costs incurred / Total estimated costs) × Total contract revenue = (60/100) × 130 = ₹78 lakh.