      Question

      A company enters into a contract to construct a

      specialized asset over 4 years. At the end of Year 2, total costs incurred are ₹60 lakh, estimated total costs are ₹100 lakh, and total contract revenue is ₹130 lakh. Which amount should be recognized as revenue till Year 2 under AS 7?
      A ₹60 lakh Correct Answer Incorrect Answer
      B ₹78 lakh Correct Answer Incorrect Answer
      C ₹65 lakh Correct Answer Incorrect Answer
      D ₹70 lakh Correct Answer Incorrect Answer
      E ₹75 lakh Correct Answer Incorrect Answer

      Solution

      Revenue recognized = (Costs incurred / Total estimated costs) × Total contract revenue = (60/100) × 130 = ₹78 lakh.