    Question

    Total factory overheads = ₹5 lakh; Direct labour hours

    = 10,000. Calculate the overhead absorption rate per labour hour.
    A ₹60/hour Correct Answer Incorrect Answer
    B ₹40/hour Correct Answer Incorrect Answer
    C ₹45/hour Correct Answer Incorrect Answer
    D ₹50/hour Correct Answer Incorrect Answer
    E ₹55/hour Correct Answer Incorrect Answer

    Solution

    • OAR = ₹5,00,000 / 10,000 hours = ₹50/hour.