📢 Too many exams? Don’t know which one suits you best? Book Your Free Expert 👉 call Now!


    Question

    A project has an expected NPV of ₹5 crore, a standard

    deviation of ₹2 crore, and a coefficient of variation of 0.4. If the company has another project with a lower expected NPV but a coefficient of variation of 0.2, which project is riskier and why?
    A First project is riskier due to lower NPV Correct Answer Incorrect Answer
    B Second project is riskier due to lower CV Correct Answer Incorrect Answer
    C First project is riskier due to higher CV Correct Answer Incorrect Answer
    D Risk cannot be compared without beta value Correct Answer Incorrect Answer

    Solution

    Coefficient of Variation (CV) = Std Dev / NPV is a measure of risk per unit return. Higher CV implies greater risk. Hence, the first project is riskier.

    Practice Next
    ask-question

    Not sure which exam is best for you Talk to our expert

    Get My Free Call