      Execution risk refers

      to:
      A Currency risk Correct Answer Incorrect Answer
      B Risk of delay or non-completion of project Correct Answer Incorrect Answer
      C Risk of fraud Correct Answer Incorrect Answer
      D Interest rate fluctuations Correct Answer Incorrect Answer

      Solution

      Execution risk includes delays, cost overruns, and technical failures during project implementation, affecting project viability.