Calculate the cost of work uncertified if total cost incurred to date is Rs. 5,00,000 and cost of work certified is Rs. 3,00,000.

A Rs. 4,00,000
B Rs. 1,00,000
C Rs. 3,00,000
D Rs. 2,00,000