      Product X requires 10 Kg of material at the rate of Rs.

      5 per Kg. The actual consumption of material for the manufacturing of product X came to 12 Kg of material at the rate of Rs. 6 per Kg. Calculate material cost variance.
      A Rs. 20 Correct Answer Incorrect Answer
      B Rs. 12 Correct Answer Incorrect Answer
      C Rs. 21 Correct Answer Incorrect Answer
      D Rs. 22 Correct Answer Incorrect Answer

      Solution

      The correct answer is D