Question

    _______ is a statement of an estimated performance to be

    achieved in given time, expressed in currency value or quantity or both.
    A Budget Centre Correct Answer Incorrect Answer
    B Budget Correct Answer Incorrect Answer
    C Budgetary Control Correct Answer Incorrect Answer
    D Budget Manual Correct Answer Incorrect Answer

    Solution

    The correct answer is B

    Practice Next

    Hey, Don't leave. If you have any queries regarding any exam let us know here.

    ask-question