      Irrigation is scheduled at IW/CPE ratio of 0.8 and the

      crop is irrigated to a depth of 5.0 cm when the CPE is:
      A 5.25 cm Correct Answer Incorrect Answer
      B 6.25 cm Correct Answer Incorrect Answer
      C 7.25 cm Correct Answer Incorrect Answer
      D 8.25 cm Correct Answer Incorrect Answer

      Solution

      IW/CPE = 0.8, IW = 5 cm => CPE = 5/0.8 = 6.25ย 