The correct answer is C
A, B and C can complete a work in 10, 20 and 15 days respectively. A left the work 3 days before the work was completed and B left 1 days after A had le...
Aman can complete a task in 12 days, while Bhanu alone can complete the same task in 18 days. Aman starts the work alone and continues for 4 days. Then,...
Raj, Sanjay and Vaibhav can separately finish a work in 20, 30 and 40 days, respectively. In how many days Raj can finish the work if he is assisted.by ...
A takes 30% longer to complete a task than B. If the total payment for the work is Rs. 11,500 and they complete the task together, how much should A be ...
If 14 men working 9 hours a day can make 24 quilts in 16 days, then in how many days 20 men working 12 hours per day will make 20 quilts?
Pawan completes in two days the same amount of work that Qureshi completes in four days. Pawan alone can finish the entire task in 15 days. How many day...
A and B together can complete a task in 12 days, while B and C together can complete the same task in 15 days. A and C together take 20 days to finish i...
‘A’ and ‘B’ can do a piece of work in 30 days and 40 days, respectively. They started working together but ‘A’ left after 9 days. Find the t...
A, B, C can do a piece of work in 11 days, 20 days, and 22 days respectively. If B works daily and is supported by A and C on alternate days beginning w...