24 male working 12 hours per day can finish a piece of work in 30 days, while 36 female working 8 hours per day can finish the sa...
1 man and 4 women can complete a work in 65 /4 days, while 3 men and 4 women can complete it in 13 /2 days. In whom many days will be 13 women complete ...
A and B together can complete a work in 7.2 days, while B and C together can complete the same work in 12 days. If A is twice efficient than C, then fin...
‘A’ and ‘B’ can do a piece of work in 20 days and 25 days, respectively. They started working together but ‘A’ left after 4 days. Find the t...
Anita and Binita have individual completion times for a task; Anita can complete it in 40 days, while Binita can do it in 56 days. Anita initiated the t...
P alone can finish a piece of work ‘M’ in 6 days while Q takes 3 days to finish it alone. P, Q and R working together can finish the work &l...
If 'A' needs 24 more days to complete a certain task working alone compared to when 'A' and 'B' work together, and 'A' is 50% more efficient than 'B', w...
‘R’ and ‘S’ can complete an assignment in 72 days and 90 days respectively while ‘R’, ‘S’ and ‘T’ together can complete the same ass...
A task can be completed in 15 days when Akash and Bittu work together. Akash is 30% more efficient than Bittu. If both started the task separately and A...
Three Typists Axe, Wye and Zed working together 3 hours per day and can type 720 pages in 12 days. In a day Wye types as many pages more than Axe as Zed...