Question
नीचे दिए गए वाक्यों
के सही अनुवाद का मिलान करें और उचित विकल्प चुनें: (i) निर्यातक को बैंक द्वारा अग्रिम भुगतान दिया गया है। – The exporter has been advanced by the bank. (ii) बैंक ने ECGC को गारंटी के लिए अनुरोध किया। – The bank requested ECGC for guarantee. (iii) राजनीतिक जोखिम बीमा कवरेज उपलब्ध नहीं है। – Political risk insurance cover is not available. (iv) ग्राहक द्वारा भुगतान पूर्व निर्धारित शर्तों के अंतर्गत किया गया। – The buyer effected payment under pre terms.Solution
व्याख्या: (i) वाक्य अनुवाद सही है। (ii) वाक्य अनुवाद सही है। (iii) वाक्य अनुवाद भी सही है। (iv) ग्राहक द्वारा भुगतान पूर्व निर्धारित शर्तों के अंतर्गत किया गया। – The buyer effected payment under predetermined terms.
A and B together can complete a work in 20 days. After working together for 8 days, B leaves, and A completes the remaining work in 16 more days. In how...
K and L can complete a work in 16 days. If K alone can complete it in 48 days, how long will L take to complete the work alone?
A and B can complete a task together in 12 days, while B alone takes 24 days to finish it. A began working alone and left after ‘x’ days, after whic...
'Asmita,' who is three times as efficient as 'Bittu,' can complete a task on her own in 15 days. 'Asmita' and 'Bittu' began working together, but after ...
- If a group of 10 boys and 15 girls together can finish a task in 30 days, and a team of 5 girls alone can complete the same task in 120 days, how long will...
A and B can complete a work together in 20 days. If A alone can complete one-fourth of the work in ‘x’ days and remaining work is completed ...
Neha and Priya are assigned a piece of work. Neha can complete 8 units of work each day, while Priya can finish the whole task alone in 32 days. If the ...
‘A’ and ‘B’ alone can do a certain work in 30 days and 40 days, respectively. Both started the work together but after ‘x’ days ‘A’ left...
12 engineers complete designing 180 blueprints in 15 days. If the goal is to complete 270 blueprints in 18 days, how many engineers are required?
40 men are engaged to dig a 4 km long drainage channel. After working 12 days, only 1/2 of the work is done. Then 8 more men are employed. Find the numb...