Question
There are eight persons P, Q, R, S, T, U, V and W with
different heights. Who is third shortest person? Statement I: P is shorter than only two persons. T is just shorter than V. Q is taller than P. Â Statement II: U is taller than R. Q is shorter than S. T is just taller than U. W is not taller than V. The question given below consists of two statements numbered I, and II given below it. You have to decide whether the data provided in the statements are sufficient to answer the question. Read all the statement and answer the question.ÂSolution
From Statement I alone: P is shorter than two persons. T is just shorter than V. Q is taller than P. We get many cases as we cannot fix the places of T and V. Case I: Q > __ > P > __ > __ > __ > __ > __ Case II: __ > Q > P > __ > __ > __ > __ > __ From Statement II alone: U is taller than R. Q is shorter than S. T is just taller than U. W is not taller than V. We get many cases as we cannot fix their positions. T > U > R , S > Q and V > W After combining statement I and II, we get: S > Q > P > V > T > U > R/W > W/R So, U is the third shortest person. Therefore, data given in both statement I and statement II together are sufficient to answer the question.
P alone can finish a piece of work ‘M’ in 6 days while Q takes 3 days to finish it alone. P, Q and R working together can finish the work &l...
- Person A is twice as efficient as Person B. Person B can complete a certain task in 32 days, while Person C takes 4 days more than Person A to finish the s...
‘A’ can do a piece of work in 15 days. ‘B’ can do 70% of the same work in 20 days. If they work together for the entire time and...
Person A is 80% more efficient than person B. A and B together can complete a certain task in 10 days, while B and C together can complete the same task...
'A' and 'B' can do a piece of work together in 30 days. They worked together for 18 days, and then left the work. The remaining job was finished by 'C' ...
A can complete a piece of work in 24 days. He worked for 21 days and then B finished the remaining work in 6 days. In how many days can A and B finish t...
Vijay can do a piece of work in 10 days and Sanjay can do the same work in 15 days. If Vijay works for 4 days and got Rs. 1680, and the remaining work w...
- 'Amit', 'Ravi', and 'Neha' can finish a piece of work in 66, 99, and 132 days respectively. They all started the work, but Amit left 8 days before the work...
- Ritu completes 50% of a project in 25 days, while Sheetal completes 40% in 32 days. Ritu works for 30 days and then stops. Find the time Sheetal needs to f...
X can do a piece of work in 22 days. He worked at it for 11 days and then Y finished it in 15 days. In how many days can X and Y together finish the work?