Question
If sin(x + y) = 3/5 and cos(x - y) = 12/13, where x, y
∈ [0, π/2], find sin(2x) + sin(2y).Solution
Let sin(x + y) = 3/5, so cos(x + y) = 4/5 using sin²θ + cos²θ = 1. Let cos(x - y) = 12/13, so sin(x - y) = 5/13 using sin²θ + cos²θ = 1. Use the identity sin(2x) + sin(2y) = 2[sin(x + y)cos(x - y)] to find: sin(2x) + sin(2y) = 2 × (3/5) × (12/13) = 72/65. Correct answer: d
‘A’ can do a piece of work in 10 days. ‘B’ can do 80% of the same work in 20 days. If they work together for the entire time and get paid Rs.140...
'Ajeet' has an efficiency that is 40% lower than 'Chirag's, where as 'Bittu' is 20% more efficient than 'Chirag'. The time difference between 'Bittu' an...
A can complete a job in 20 hours. B alone can complete the same job in 15 hrs. A work for 9 hrs and then the remaining job is completed by B. How many h...
‘A’ and ‘B’ can do a piece of work in 30 days and 20 days, respectively. If they started the work together and worked on it for 4 days, then fin...
A can finish a job in 30 hours while B can finish it in 20 hours. If C is (300/7)% more efficient than A and B together, then find the time taken by C a...
A can complete a piece of work in 10 days , and B can complete the same work in 15 days . They start working together, and after some days A leaves....
‘X’ and ‘Y’ together can do a work in 16 days. If ‘X’ increases his efficiency by 75% and ‘Y’ decreases his efficiency by 25%, then the...
Meena and Mohit, alone can complete a work in 12 days and 18 days, respectively. They started the work together and left after 4 days such that the rem...
P and Q together can do a piece of work in 15 days, Q and R together can do it in 18 days. P starts the work and works on it for 5 days, then Q takes it...
A contractor hired 50 workers to complete a work in 80 days. After 50 days, it was found that only 1/4th of the work was completed. Find the number of e...