Question
A sum of ₹15,000 is divided into two parts. One part
is invested at 10% simple interest per annum, and the other part is invested at 15% simple interest per annum. After 2 years, the total interest earned is ₹3,500. How much was invested at 10%?Solution
Let the amount invested at 10% be ₹x, and the amount invested at 15% be ₹15,000 - x. Interest from the first part = (x × 10 × 2) / 100 = 0.2x. Interest from the second part = ((15,000 - x) × 15 × 2) / 100 = 0.3(15,000 - x). Total interest = ₹3,500, so 0.2x + 0.3(15,000 - x) = 3,500 0.2x + 4,500 - 0.3x = 3,500 -0.1x + 4,500 = 3,500 -0.1x = -1,000 x = ₹10,000. Correct option: d
A, B, and C together can complete the assignment in 8 days. B and C together take (48/5) days, and C alone completes half in 8 days. Find the ratio of t...
'M' alone finishes a project in 30 days. 'M' and 'N' together can complete the same project in 16(2/3) days. How many days would 'N' need to do the proj...
'Sumit' can complete (3/8) of a job in 24 days, where as 'Sumit' and 'Tarun' together can finish it in 16 days. Calculate the time 'Tarun' needs to comp...
‘D’ and ‘E’ together can finish a task in 40 days, while ‘E’ and ‘F’ together can finish the same task in 30 days. ‘D’ and ‘E’ t...
168 unit of work can be completed by P alone in 28 days. P started working alone and joined by Q after 10 days such that they completed the remaining wo...
A’ and ‘B’ together can complete a work in 25 days while ‘A’ takes 30 days to complete the same work alone. If ‘C’ is 20% more efficient t...
Ishan alone can do a certain piece of work in 'w' days and Bhanumati can do it in '2w' days (w is a positive integer). Both together can do the work in ...
Komal and Seema individually can complete a task in ‘2a’ hours and ‘7a’ hours respectively. If they together can complete half of the work in 7...
A and B together, B and C together and A and C together can complete a piece of work in 40 days, 30 days and 50 days respectively. Find the ratio...
A and B can complete a work together in 30 days. If A alone can complete one-third of the work in ‘x’ days and remaining work is completed b...