Question
Quantity-I: 'Asmita' is able to finish 32% of a task in
16 days. 'Ben' can complete the same task in 10 days fewer than 'Asmita'. Calculate the time it would take for both 'Asmita' and 'Ben' to complete 90% of the task together. Quantity-II: 18 days In the given problem, two quantities, I and II, are presented. You are required to solve both quantities and determine the correct relationship between them.Solution
ATQ, Quantity I: Time taken by ‘Asmita’ to complete the whole task = 16/0.32 = 50 days Time taken by ‘Ben’ to complete the whole task = 50 – 10 = 40 days Let the total task be = 200 units Efficiency of ‘Asmita’ = 200/50 = 4 units/day Efficiency of ‘Ben’ = 200/40 = 5 units/day Required time taken = 0.9 × 200/9 = 20 days Quantity II: 18 days
Select the option that is related to the third number in the same way as the second number is related to the first number.
72 : 101 :: 98 : ?
Select the option that is related to third letter- cluster in the same way as the second – letter cluster is related to the first letter- cluster.
...14 : 75 : : ?
In the following question, four number pairs are given. In each pair the number on left side of (-) is related to the number of the right side of (-) wi...
In each of the following questions, choose that set numbers from the four alternative sets, that is similar to the given set.
Given set:Â [13...
 What is related to Menu as Syllabus is related to Course?
If SIT = 19920 and SITE = 199205, then SIGHT =
Select the option that is related to third letter- cluster in the same way as the second – letter cluster is related to the first letter- cluster.
E × I : 25 × 81 ∷ K × P : ?
PINE : 5945 :: HERO : 8585 :: JUMP : ?