Question
A and B can complete a piece of work in 12 days and 18
days, respectively. They start working together but A leaves after 6 days. How many more days will it take for B to finish the remaining work?Solution
A's work rate = 1/12 (work done in one day) B's work rate = 1/18 Combined Work Rate: Work done by A and B together in one day = (1/12) + (1/18) = (3/36) + (2/36) = 5/36 Work Done in 6 Days Together: Work done in 6 days = 6 × (5/36) = 30/36 = 5/6 of the work. Remaining work = 1 - 5/6 = 1/6 of the work. Time Taken by B to Complete the Remaining Work: B can complete the remaining work in: Time = Remaining work / B's work rate = (1/6) / (1/18) = (1/6) × (18/1) = 3 days. Correct Answer: d
Which law states that the total current entering a junction is equal to the total current leaving the junction?
A particle starts from rest and accelerates uniformly at 2 m/s² for 10 seconds, then moves with constant velocity for 5 seconds, and finally decelerat...
An image formed by a plane mirror is ______.
Which of the following does not affect the value of acceleration due to gravity?
Which law describes the relationship between the force applied to a spring and its extension or compression?
Which of the following is not a characteristic of simple harmonic motion (SHM)?
Water flows in a horizontal pipe of non-uniform area of cross-section at a pressure difference of 1.6 cm of mercury. If the velocity of water at the la...
What is found in frequency modulation?
Which one of the following is called a red planet?
The electric and magnetic fields of an electromagnetic wave are _____________