Start learning 50% faster. Sign in now
P. let total work to be done (LCM of 14 & 5) = 70 unit One day work of A = 70/14 = 5 unit One day work of B = 70/5 = 14 unit One day work of A & B = 14+5 = 19 unit In three days they will work = 3×19 = 57 unit Remaining work = 70-57 = 13 unit Since work is started by B Time taken by B to complete rest work = 13/14 = 0.9 days Total time taken to finish the work = 3+0.9 = 3.9 days (approx) Q. Pipe M can fill one-third of the tank in 4 hrs. Pipe M will fill this tank in 4×3 = 12 hrs. Pipe M can fill 20% of the tank in 3 hrs. Pipe M will fill this tank in 5×3 = 15 hrs. Both pipe M & N has to fill (LCM of 12 & 15) = 60 unit Pipe M will fill in 1 hrs. = 60/12 = 5 unit Pipe N will fill in 1 hrs. = 60/15 = 4 unit Both Pipe together will fill = 5+4 = 9 unit Since tank is half filled, hence both tap has to fill only 30 unit Time taken to fill the tank completely = 30/9 = 3.33 hrs. R. let x men included Then 30 men completes the work in 20 days And (30+x) men will complete in 3/5 of 20 days = 12 days 30×20 = (30+x) ×12 X = 20 men Hence we can see that Q < P < R
A new Laptop has been produced that weighs less, is smaller and uses less power than previous Laptop models. Which of the following technologies has bee...
Which of the following is known as the process of viewing cross-tab with a fixed value of one attribute?
Which of the following extensions is used to save an image on a computer?
Data duplication wastes the space, but also promotes a more serious problem called
With respect to computers, which one of the following best describes phishing?
Which generation of computer systems typically employs Real-Time Operating Systems (RTOS)?
The minimum number of page frames that must be allocated to a running process in a virtual memory environment is determined by ____________
Which of the following is different from other ?
An E-mail address is composed of :
The highest level in the hierarchy of data organization is called