Question
The combined average production for four years of
companies A and C is what percentage (rounded off to 2 decimal places) more/less than the combined average production for four years of companies B and D? The bar graph below shows the production of coffee (in lakh tons) by four companies A, B, C and D over a period of four years from 2010 to 2013. Study the graph and answer the question that follows.Solution
From the chart: A total = 60+90+140+220 = 510
C total = 50+190+180+250 = 670
A+C total = 510+670 = 1180 β Average = 1180/4 = 295
B total = 70+100+150+210 = 530
D total = 120+170+200+260 = 750
B+D total = 530+750 = 1280 β Average = 1280/4 = 320
Percentage difference = ((295 - 320) / 320) Γ 100 = -7.81%
P can do a piece of work in 15 days, Q can complete double the work in 40 days and R can do the work in 20 days. If all of them together earn Rs. 3000, ...
- Alex and Ben can complete a job individually in 14 days and 21 days, respectively. If they take turns to work one day each, beginning with Alex, how long w...
βXβ and βYβ can do a task together in 15 days. If βXβ alone takes 25 days to complete it, then how much time will βYβ take to finish the...
βPβ and βQβ can complete a task together in 24 days. If βPβ alone can do it in 40 days, find the number of days βQβ alone will take to f...
A can complete a work in 40 days. B takes 20 days less than A to complete the same work. In how many days can both of them together complete 90% of the ...
P can do a piece of work in 30 days. Q do the same work in 40 days. R can do it in 35 days. P and R worked for 4 days and handed it to Q. Q worked for s...
X can do a piece of work in 15 days. He worked at it for 3 days and then Y finished it in 16 days. In how many days can X and Y together finish the work?
A job is done by 15 men in 30 days and 30 women in 20 days. How many days will it take for 8 men and 12 women to finish the work?
P can do a piece of work in 20 days, Q can do the same piece of work in 24 days while R can do it in 30 days. They started working together but after 4 ...
12 engineers complete designing 180 blueprints in 15 days. If the goal is to complete 270 blueprints in 18 days, how many engineers are required?