A's work rate: A completes the work in 6 days, so A does 1/6 of the work in 1 day. B's work rate: B completes the work in 9 days, so B does 1/9 of the work in 1 day. C's work rate: C completes the work in 11 days, so C does 11/11 of the work in 1 day. Combined work rate: Together, they complete: Find the combined rate :
Time to complete the work : To complete 1 full work, the time taken is:
= or 2(52/73) days