Question
A group of workers can complete a project in 30 days if
they work 6 hours a day. However, due to some constraints, the number of workers available is reduced by 25%, and they can only work 4 hours a day. How many additional days will it take for the reduced workforce to complete the project?Solution
ATQ, Let's calculate how many additional days it will take for the reduced workforce to complete the project. Number of workers = W (let's assume there are W workers) Hours worked per day = 6 Total days to complete the project = 30 days Total work = 30 days × 6 hours/day × W workers = 180W hours Number of workers available = 75% of W (reduced by 25%) Hours worked per day = 4 Total work = (additional days + 30 days) × 4 hours/day × 0.75W workers Now, we want to find out how many additional days it will take for the reduced workforce to complete the project, so we need to set up an equation: 180W = (30 days + additional days) × 4 × 0.75W Now, let's solve for additional days: 180W = (30 + additional days) × 3W Divide both sides by 3W: 60 = 30 + additional days Subtract 30 from both sides: additional days = 60 - 30 = 30 days
What does HTML stand for in web technology?
Which layer of the OSI model provides flow control, error checking, and reliability in data transmission?
In C programming, which header file is commonly used to work with DMA?
What is the data transmission direction in a Token Ring network?
Store data in single table
State true/false
Once the email is compromised, all other sites and services online associated with this email can be compromised.
Which of the following backup types provides the fastest backup and recovery performance but requires the most storage space?
What is the purpose of a semaphore in synchronization?
In which programming language is dynamic memory allocation commonly used?
What does the term "phishing" refer to in the context of cybersecurity?