Question
Paras and Punit started a business by investing Rs.
18,000 and Rs. 24,000 respectively. Paras also worked as the active manager and for that he is entitled to receive a commission which is equal to 30% of profit. If the difference between the amount received by Paras and Punit at the end of the year is Rs. 2000, then find the profit (before commission was given to Paras) earned by them.Solution
Let the profit earned before commission was given to Paras be Rs. β100xβ Commission of Paras = 100x Γ 0.3x = Rs. 30x Ratio of profit shares of Paras to Punit = 18000:24000 = 3:4 Profit earned by Paras = (100x β 30x) Γ (3/7) = Rs. 30x Profit earned by Punit = (100x β 30x) Γ (4/7) = Rs. 40x According to the question 30x + 30x β 40x = 2000 Or, 20x = 2000 So, x = 100 So, required profit = 100 Γ 100 = Rs. 10,000
x men can finish a work in y days. 0.9x women can finish 1/3rd of the same work in (y - 8) days. If 0.8x women can complete 1/3rd work in 36 days. Find ...
Team A can built a project in 4 hours less than the time taken by Team B to built the same project.
The ratio of the strength of Team A to that o...
A, B and C can mow a field in 36 days, 72 days and 54 days respectively. All the three began the work together on January 1, 2016, but A left 8 days and...
βFβ is 66.67% more efficient than βGβ. βGβ worked alone for 10 days, and then βFβ completed the rest of the work. If the entire job was ...
- A woman is one-third as efficient as a man. How much time will 9 women take to complete a job that is 75% of the work done by 10 men in 12 days?
A boy(labour) was appointed by a manager on the term that he would be paid Rs 55 for each day of his work but would be fined at the rate of Rs 5 per day...
Anil alone can finish some work in 50 days. Anil and Aman completed the work together and earned Rs. 9,000 as wage. If Aman's wage share is Rs. 3,600, t...
Rahul can complete a work in 12 days and Ayush in 15 days. If they work together for 3 days, then the fraction of work that will be left is:
βMβ and βNβ together can do a work in 20 days. If βMβ increases his efficiency by 25% while βNβ decreases his efficiency by 50%, then t...
Karan is five times as efficient as Varun and twice as efficient as Arjun. If Varun takes 30 days to finish some work, then find the time taken by Karan...