Question
The term ‘Gross’ is being used for Gross
Domestic Product (GDP) because its computation does NOT exclude which of the following factors?Solution
Gross Domestic Product ( GDP ) is the monetary value of all finished goods and services made within a country during a specific period. GDP provides an economic snapshot of a country, used to estimate the size of an economy and growth rate. · "Gross" (in " Gross Domestic Product") indicates that products are counted regardless of their subsequent use. A product can be used for consumption, for investment, or to replace an asset. In all cases, the product's final "sales receipt" will be added to the total GDP figure. · In contrast, "Net” in the Net Domestic Product (NDP) takes into account the depreciation of the asset used. NDP = GDP – Depreciation During production process fixed capital assets like machines, building etc. get depreciated and their value goes down. This is known as normal wear and tear of machinery or consumption of fixed capital or depreciation.
P, Q & R can finish a work in 10 days, 15 days, and 20 days, respectively, working alone. P and Q work on the first day, P and R work on the second day,...
The ratio of efficiencies of Ajay and Bijay is 7:8, respectively. Ajay and Bijay together can complete the total work in 24 days. In how many days will ...
A and B can complete a task together in 12 days, while B alone takes 24 days to finish it. A began working alone and left after βxβ days, after whic...
A work can be completed by βAβ and βBβ, alone in 18 days and 10 days, respectively. Find the number of days taken by βCβ to complete the sam...
20 men can complete a piece of work in 40 days. βxβ men started the work and after 35 days 64 more men joined them so that whole work was finished i...
A, B, and C each have different rates of completing a task; A can finish it in 36 days, B in 60 days, and C in 30 days. Initially, they begin the work c...
Pawan, Bittu, and Raju can individually complete a task in 36 days, 60 days, and 30 days, respectively. They all begin working together, but Raju stops ...
βPβ, βQβ, and βRβ can complete a task in 10 days, 15 days, and 20 days, respectively. βPβ starts the task alone a...
A team of 40 men is assigned to finish a project within 24 days. They began the task simultaneously. To complete the project 6 days ahead of the planned...
- A firm assigned 10 technicians to complete an assignment in 30 days. After 12 days of work, 4 technicians were moved to another location. What is the exten...