Question
What will be the output of the following code when the
pop method is executed? class Stack: Â Â def __init__(self): Â Â Â Â self.stack = [] Â Â def push(self, item): Â Â Â Â self.stack.append(item) Â Â def pop(self): Â Â Â Â if not self.isEmpty(): Â Â Â Â Â Â return self.stack.pop() Â Â Â Â else: Â Â Â Â Â Â return "Stack is empty" Â Â def isEmpty(self): Â Â Â Â return len(self.stack) == 0 s = Stack() s.push(10) s.push(20) s.push(30) output = s.pop() print(output)Solution
In the code, a stack is implemented using a list. The push method adds elements to the stack, and the pop method removes the top element. Initially, 10, 20, and 30 are pushed onto the stack. When pop is called, it removes the last element added, which is 30. Thus, the output is 30. Why Other Options Are Wrong: A) 10: This option is incorrect because 10 is the first element added to the stack and is at the bottom, not the top. B) 20: This option is incorrect as 20 is the second element, not the last pushed, so it remains in the stack after 30 is popped. D) Stack is empty: This option is incorrect because the stack is not empty; it still contains 10 and 20 after 30 is removed. E) None: This option is incorrect as it suggests that there is no output, while there is indeed a valid output being printed.
‘A’ can do a piece of work in 15 days. ‘B’ can do 60% of the same work in 20 days. If they work together for the entire time and get paid Rs.145...
- 40 women working 10 hours a day take 12 days to complete a project. How many women working for 7 hours a day are needed to complete twice the given project...
Bholu and Golu have teamed up to finish a task. On his own, Bholu can complete 5 units of work each day. Golu, when working solo, can finish the entire ...
A and B working together, can do a piece of work in 4(1/2) hours. B and C working together can do it in 3 hours. C and A working together can do it in 2...
P can complete a job in 30 days. Q alone can complete the same job in 20 days. P works for 18 days and then the remaining job is completed by Q. How man...
A and B can complete a work together in 18 days. If A alone can complete one-third of the work in ‘x’ days and remaining work is completed b...
P and Q can finish a job working together in 24 days. P completes two-thirds of the task in 'd' days, and Q finishes the rest in ...
Pipe A alone can fill 75% of a cistern in 18 minutes. When both Pipe A and Pipe B are opened together, they can fill the entire cistern in 33 minutes. H...
P’s 4 days work is equal to Q’s 5 days work. If P and Q together can complete the work in 25 days then how much time Q will take to complete 40% of ...
- 50% of the work done by Meena in 2 days is equal to 25% of the work done by Lata in 5 days. If Meena can complete the job alone in 10 days, then how long w...