Question
In the context of Indian economy, which of the following
is/are the purpose/purposes of ‘Statutory Reserve Requirements’? 1. To enable the Central Bank to control the amount of advances the banks can create 2. To make the people’s deposits with banks safe and liquid 3. To prevent the commercial banks from making excessive profits 4. To force the banks to have sufficient vault cash to meet their day-to-day requirements Select the correct answer using the code given below.Solution
1 is definitely correct as CRR. SLR is used to control money supply and credit off take. 2 may or may not be correct, to make people's deposit safe, capital adequacy ratio is the norm. 3 is definitely wrong as to control excess profit, margins would have to be reduced, not CRR, SLR.
Ratio of the work done by P, Q and R in one day is 8:5:9 respectively. They all together can complete the work in 40 days. Q and R worked on it for 32 d...
- Neha and Seema can finish a work in 10 days and 25 days, respectively, when working alone. Neha started the work. After how many days should Seema join to ...
X, Y, and Z alone can complete a language translation in 60, 90, and 36 days respectively. They started working together, but after 5 days, Z left the j...
P’s 4 days work is equal to Q’s 5 days work. If P and Q together can complete the work in 20 days then how much time Q will take to complete 40% of ...
- Pooja can finish a task by herself in 12 days, while when working together, Manju and Pooja can complete the same task in 6 days. Manju starts the work alo...
32 workers can complete a task in 18 days. They all started together, but after how many days should 12 workers quit so that the task gets completed in ...
- Ayaan and Kabir started working together on a task. Ayaan does 4 units per day and Kabir can finish the full task in 25 days alone. The total work is 100 u...
20 men can finish a work in 12 days by working 7 hours a day. How many more men are needed to finish the work in 10 days by working 8 hours a day?
- 50% of the work done by Meena in 2 days is equal to 25% of the work done by Lata in 5 days. If Meena can complete the job alone in 10 days, then how long w...
20 men take 15 days to finish some work. 24 women can finish the same work in 20 days. If the ratio of efficiencies of each man and woman is p:q, respec...