Question
During the execution of a construction contract, the
following events occurred: · Materials worth ₹5 lakh were damaged due to heavy rainfall and became unusable. · After the heavy rainfall, the client requested to construct an extra parking shed which was not part of the original contract. The contractor raised a claim of ₹25 lakh for this additional work. How should these items be treated in contract costing?Solution
The material loss of Rs.5 lakh is considered a normal loss due to unavoidable occurrence of rainfall at the site. Normal loss is part of the contract cost and therefore will be charged to contract cost. Note - If the loss was abnormal (fire/theft), then it would have been charged to Costing P&L The Rs.25 lakh of additional shed is extra work at the request of the client. As it was not a part of the original contract, it represents extra or variation work. The amount claimed by the contractor will be credited to contract account.
Onion production is related to
Which of the following is not a method of group communication?
Which of the following parts of the stomach is called “True stomach”?
Which of the following is not matched correctly?
Orobanche is _____ type of parasitic weed.
Which of the following is a ‘P’ solubilizing bacteria?
Following is an example of sedimentary rock
The soils of very cold climates which are defined as containing permafrost within two meters of the soil surface belongs to the order
Which of the following species of Rhizobium bacteria is responsible for nodule formation in Soyabean?
Which of the following statement is incorrect?