Question
During the execution of a construction contract, the
following events occurred: ·       Materials worth ₹5 lakh were damaged due to heavy rainfall and became unusable. ·       After the heavy rainfall, the client requested to construct an extra parking shed which was not part of the original contract. The contractor raised a claim of ₹25 lakh for this additional work. How should these items be treated in contract costing?Solution
The material loss of Rs.5 lakh is considered a normal loss due to unavoidable occurrence of rainfall at the site. Normal loss is part of the contract cost and therefore will be charged to contract cost. Note - If the loss was abnormal (fire/theft), then it would have been charged to Costing P&L The Rs.25 lakh of additional shed is extra work at the request of the client. As it was not a part of the original contract, it represents extra or variation work. The amount claimed by the contractor will be credited to contract account.
The last period’s forecast was 70 and demand was 60. What is the simple exponential smoothing forecast with alpha of 0.4 for the next period...
Arrange the following milestones in the history of the European Union in the correct chronological order (from earliest to most recent):
I. The s...
If the elasticity of demand is -2 and price charged by the firm is Rs.10 and quantity sold is 15 units. What is the Lerner’s Index of Monopoly power?...
During the planning period, highest growth rate was achieved duringÂ
GNP exceeds NNP by:
R-square is the fraction of
Which of the following tests use rank sums?
Holly, Brian, Fred, Tracy, and Melanie have income elasticities for veggie burgers as given below:
Person Income elasticity o...
Which of the following institutions is primarily concerned with promoting stability in the international monetary system through surveillance and lending?
When oligopolistic firms co-operate and work as cartel, then output produced is ______ than perfect competition and ______ to Monopoly