Question
Reserve Bank of India has launched the Inflation
Expectations Survey of Households (IESH) which will provide useful inputs for?Solution
The Reserve Bank of India has launched the Inflation Expectations Survey of Households (IESH) which will provide useful inputs for monetary policy. In the January 2023 , the survey will be conducted across 19 cities. It aims to capture subjective assessments of price movements and inflation, based on individual consumption baskets. The survey seeks qualitative responses from households on price changes (general prices as well as prices of specific product groups) in the three months ahead as well as in the one-year ahead period and quantitative responses on current, three months ahead and one year ahead inflation rates. The survey will be conducted in Ahmedabad, Bengaluru, Bhopal, Bhubaneswar, Chandigarh, Chennai, Delhi, Guwahati, Hyderabad, Jaipur, Jammu, Kolkata, Lucknow, Mumbai, Nagpur, Patna, Raipur, Ranchi and Thiruvananthapuram. The agency — Hansa Research Group, Mumbai — has been engaged to conduct the survey of this round on behalf of the central bank.
Pawan, Bittu, and Raju can individually complete a task in 36 days, 60 days, and 30 days, respectively. They all begin working together, but Raju stops ...
- Pipe βXβ can fill a tank 15 minutes faster than Pipe βYβ. If both are opened together, they can fill the tank in 18 minutes. If 180 litres of water...
A man travelled a total distance of 200 km. He travelled first 150 km on car with a speed of 30 km/h and rest of the distance on bike whose speed is 20 ...
A can complete a work in 18 days and B can complete the same work in 24 days. They work together for 6 days, after which A leaves. In how many more days...
Worker βPβ can finish a task in 54 days, which is 18 days quicker than worker βQβ. If they take turns daily starting with βPβ, find the tota...
Arun and Bala, alone can complete a work in 20 days and 30 days, respectively. They started the work together and left after 8 days such that the remai...
18 men can finish a work in 15 days by working 8 hours a day. How many more men are needed to finish the work in 12 days by working 6 hours a day?
A can finish a piece of work in 12 days and B can finish it in 18 days. They work together for 4 days, after which B leaves. In how many more days will ...
P and Q together can do a job in 6 days, Q & R can finish the same work in 60/7 days. P started the work and worked for 3 days. Q & R continued ...
X can do a piece of work in 36 days. He worked at it for 6 days and then Y finished it in 20 days. In how many days can X and Y together finish the work...