Question
Which of the following is/are correct regarding Capital
Conservation Buffer? I It is required when there is excess growth in bank’s credit portfolio II It is 2.5% of Risk Weighted Assets (RWA) III It is required to be maintained over and above the minimum regulatory capital IV It intends to ensure that banks are able to absorb losses even in economic distressSolution
Capital Conservation Buffer (CCB) is designed to absorb losses during periods of financial and economic stress. Financial institutions will be required to hold a capital conservation buffer of 2.5% to withstand future periods of stress, bringing the total common equity requirement to 7% (4.5% common equity requirement and the 2.5% capital conservation buffer). The capital conservation buffer must be met exclusively with common equity. Financial institutions that do not maintain the capital conservation buffer faces restrictions on payouts of dividends, share buybacks, and bonuses.
5 Pandavas can do a work in 18 days, 4 Kauravas can do the same work in 30 days. Now, in how many total days the total work be finished if 1 Panadva and...
Ankit can complete a task in 16 days, while Bina alone can complete the same task in 24 days. Ankit starts the work alone and continues for 6 days. Then...
'P', 'Q', and 'R' can individually complete a task in 20, 24, and 30 days, respectively. They all started working together, but '...
Anuj and Bishnu can complete a task together in 24 days, Bishnu and Raj can complete the same task together in 48 days, and Anuj ...
The amount of work completed by 24 men in 5 hours is equivalent to the work done by 21 women in 8 hours. A team of 33 men, working 6 hours daily, can fi...
A can finish a job in 15 days and B can finish the same job in 20 days. In how many days can they finish it working together?
The team of A B and C was supposed to complete a piece of work. Working alone, A could have completed the same work in 190 hours. B could have completed...
A and B can do a piece of work in 15 and 20 days respectively. They work together for 5 days, then A leaves. How long will B take to finish?
Amit is 66(2/3)% more efficient than Vivek who can do the same work in 25% more time than Sameer. If Amit and Sameer together can complete 70% of work ...
P and Q together finish a piece of work in 12 days. R works at half the efficiency of P. Q alone can finish the work in 30...