Question
Which of the following statements about Net Owned Fund
(NOF) requirement for ARCs is true? Refer to the following information to answer the next 4 questions (Q15 to Q17) The asset reconstruction industry is set to clock the best growth this fiscal as their asset under management is expected to increase by almost 10% to Rs 1.1 lakh crore. The 29-player ARC industry began its journey in the second half of 2002 and has since undergone radical regulatory changes and challenges. With the beginning of operation of public sector National Asset Reconstruction Co. and rising popularity of the Insolvency and Bankruptcy Code effective from May 2016 also pose challenge for the ARC industry. Another major challenge is the steep fall in banks' non-performing assets, which is set to fall to under 5% by March, down from over 11% in FY18. Assets under management of ARCs are set togrow 9.8% to a five-year high this fiscal, driven by a few large transactions to Rs 1.19 lakh crore.Solution
The minimum Net Owned Fund (NOF) for ARCs shall be Rs.300 crore on an ongoing basis from October 11, 2022. Therefore, option C is the correct answer. Options A, B, and D are incorrect as they provide incorrect information, and option E is incorrect as there is a change in the NOF requirement.
A2 type ‘P’ pipes can fill a tank in 450 hours, while B2 type ‘Q’ pipes can fill the same tank in 6...
X can do a piece of work in 25 days. He worked at it for 5 days and then Y finished it in 24 days. In how many days can X and Y together finish the work?
P, Q & R can finish a work in 10 days, 15 days, and 20 days, respectively, working alone. P and Q work on the first day, P and R work on the second day,...
40 laborers were hired to finish a construction job in 50 days. After 35 days of work, only 70% of the job was done. How many additional laborers are ne...
A can do a piece of work in 24 days. B can do the same work in 16 days and C can do the same work in 5/4th time required by both A and B together. A an...
A alone can do a piece of work in 10 days and B alone in 15 days. In how many days will they finish the work together?
12 man can make a wall in 6 days. How many men required to complete the same work in 3 days ?
P and Q can complete a work in 36 days and 54 days, respectively. P, Q and R together can complete the work in 18 days. If R get a total wage of Rs. 594...
P and Q can separately finish the work in 15 days and 25 days respectively. They worked together and P left the work, so Q complete the remaining work i...
It takes a team of either 20 boys or 35 girls, 27 days to achieve a sales target. How many days will it take for a team consisting of 21 boys and 42 gir...