Question
Which of the following areas are monitored in a PCA
framework for evaluating whether the Non Banking Finance Companies (Deposit-taking and Non-deposit taking) is to be brought under the ambit of Prompt corrective action or not? Read the following passage and answer the next 5 question Central Bank along with a clutch of other lenders was placed under RBI's prompt corrective action (PCA) in 2017 after the regulator found some state-run lenders were in breach of its rules on regulatory capital, bad loans and leverage ratios. Since then all the lenders except Central Bank have improved their financial health and come off RBI's PCA list. A bank under PCA faces greater scrutiny by the regulator and may face lending and deposit restrictions, branch expansion and hiring freezes and other limitations on borrowings. The RBI introduced these norms at a time when Indian lenders were battling record levels of soured assets, prompting the RBI to tighten thresholds. Source: economictimesSolution
PCA Framework monitors the NBFCs in the following areas 1.   NBFCs-D and NBFCs-ND are monitored in the areas of Asset Quality and Capital 2.   CICs are monitored in the areas of Asset Quality, Capital and Leverage.  PCA Framework tracks the following indicators of NBFCs 1.   For NBFCs-D and NBFCs-ND the framework will track indicators like Capital to Risk (Weighted) Assets Ratio (CRAR), Net NPA Ration (NNPA), Tier-1 Capital Ratio. 2.   For CICs, the indicators are NNPA, Adjusted Net Worth/Aggregate Risk Weighted Assets and Leverage Ratio.  The NBFCs will be put under the PCA Framework on the basis of the audited Annual Financial Results along with the Supervisory Assessment done by the RBI. However, RBI can impose this framework during the course of the accounting year itself if the existing circumstances so demand. Â
P works thrice as fast as Q, whereas P and Q together can work four times as fast as R. If P&Q and R together work on a job, in what ratio should they s...
- Neha and Seema can finish a work in 10 days and 25 days, respectively, when working alone. Neha started the work. After how many days should Seema join to ...
P, Q, and R can do a project individually in 10, 25, and 20 days. P and Q begin the project, but after 2 days, P is replaced by R. How many more days wi...
The time taken by ‘A’ to build a wall alone is 45% more than the time taken by him to build it along with ‘B’. ‘B’ will take how much percen...
Akhil and Nikhil together can complete a work in 12 days while Nikhil alone takes 18 days to complete 25% of the work. If the efficiency of Sachin is 20...
Anita and Binita have individual completion times for a task; Anita can complete it in 40 days, while Binita can do it in 56 days. Anita initiated the t...
(x + 3) workers complete 50% of work in 4 days at 5 hours/day. (x + 1) workers finish the rest in 5 days at 6 hours/day. Find x.
20 boys can dig a pit in 15 days, while 5 men can dig the same pit in 6 days. In how many days will 10 boys and 1 man together dig the pit?
A can complete a work in 18 days and B in 24 days. They work together for 4 days, then C (who alone can complete the work in 36 days) joins them. Find t...
A can finish a piece of work in 10 days and B can finish it in 15 days. If both work together, in how many days will the work be completed?