Question
Why Treasury rates are significantly lower as compared
to other rates?Solution
Treasury bonds are considered risk-free assets, meaning there is no risk that the investor will lose their principal i.e. investors that hold the bond until maturity are guaranteed their principal or initial investment. There is no credit risk and with lower risk, the return is also lower. Furthermore, Treasury bills and bonds are purchased by the financial institutions for fulfilling their various regulatory requirements (like SLR). For the bulk purchase, their prices rise and yields turn low. The amount of capital a bank is required to hold in support of investment in treasury bills and bonds is lower as compared to capital to be held for other instruments with very low risk.
20 men can finish a work in 220 days, but at the end of 90 days, 20 additional men are employed. In how many more days will the work be completed?
Ram can do a piece of work in 12 days and Shyam can do the same work in 20 days. They both started work together, Ram left 4 days before the completion ...
- A team of 6 workers, each working 8 hours per day, can build a 200-metre-long wall in 15 days. How many workers would be needed to construct a 300-metre-lo...
114 unit of work can be completed by P alone in 19 days. P started working alone and joined by Q after 10 days such that they completed the remaining wo...
‘A’ alone can complete a work in 40 days while ‘A’ and ‘B’ together can complete the same work in 20 days. How much ...
'A' alone can do some work in 15 days. 'B' is 40% more efficient than 'A'. 'A' worked alone for 8 days and left. How much time (in days) does 'B' need t...
It is given that 40% of the work completed by Lokesh is equal to 30% of the work completed by Meena. If Lokesh alone can complete the entire work in 28 ...
P and Q can complete a work in 26 days and 39 days, respectively. P, Q and R together can complete the work in 13 days. If R get a total wage of Rs. 585...
If a task can be completed by either 10 boys or 12 girls in 10 days, how long will it take for a team of 5 boys and 2 girls worki...
X can do a piece of work in 15 days. He worked at it for 3 days and then Y finished it in 16 days. In how many days can X and Y together finish the work?