Yojana (PMKVY) has been launched in a bid to empower India’s youth with employable skills by making over 300 skill courses available to them? Jammu & Kashmir is one among the youngest states of India with more than 54% of the total population below 25 years of age. However, our formally skilled workforce is approximately 2% which is dismally low as compared to other states of India. This is universally accepted fact that the economic growth of the country, and strength of any nation is mainly dependent on knowledge and skill based human resource. Looking at rapidly increasing demand supply gap, it is very important for an organization to ensure an adequate supply of skilled manpower and their optimize use. At the same time the population of other states is ageing fast and it is projected to increase 15% by 2030. The market may suffer with the labour shortage due to aging population. J&K has the advantage as compared to other states of India, because its youngest population is estimated to be 6 lakh as per 2011 census. Jammu and Kashmir has second worst unemployment rate among states/Union territories in the country. Governmental efforts especially in the recent past, in the arena of skill development – The National Skill Development Mission – launched by the Ministry of skill Development and Entrepreneurship in July 15 2015, aims to create convergence across sectors and states in terms of skill training activities to ‘unskilled’ and ‘semiskilled’ youth of J&K.Solution
The Ministry of Skill Development and Entrepreneurship (MSDE) has launched Pradhan Mantri Kaushal Vikas Yojana (PMKVY) 3.0, in a bid to empower India’s youth with employable skills by making over 300 skill courses available to them.
Aaru Swati and Rajni can finish a work in 4 days if they work together. However, Aaru alone will take 9 days to complete the work, and Swati alone will ...
- A task can be done by ‘p’ men in 32 days. If the team had 8 more men, the work would finish in 24 days. Find the value of ‘p’.
‘A’ can do a piece of work in 10 days. ‘B’ can do 80% of the same work in 20 days. If they work together for the entire time and get paid Rs.140...
'B' is 20% more efficient than 'A.' 'A' began working on a task alone and continued for 8 days, after which 'B' took over and completed the remaining wo...
- C is 50% more efficient than D and can complete a task in 18 days. C and D work together for 6 days, after which D leaves. In how many more days will C fin...
Abhay, Beer, and Tittu have individual work completion times of 12 days, 24 days, and 36 days, respectively. They Started working together on a task. Af...
A fence is constructed using 900 wooden planks. ‘X’ alone can place 10 planks per minute, while ‘Y’ alone can complete the fence in 100 minutes....
Working together, A and B can do a certain work in 45 days. They work together for 10 days. They complete the remaining work in 28 days with the assista...
In an office, an employee plans to do a work in 20 days with 6 laptops. But after 10 days, he found that only 40% of the work is done with the laptops w...
(x + 6) workers complete 40% of a job in 8 days by working 5 hours/day. The remaining work is done by (x + 2) workers in 16 days working 5 hours/day. Fi...