Question
P can do a piece of work in 20 days, Q can do the same piece of work in 24 days while R can do it in 30 days. They started working together but after 4 days ‘P’ left the work and the remaining work was completed by Q and R together. Find in how many days will the work be completed?
More Difficult level Section Tests Questions
- Find the equation if a point P(x, y) is equidistant from A(7, 3) and B(-3, 7).
- A merchant made a profit of Rs. 600 on selling a gadget. Had the cost price been Rs. 400 lower and the selling price Rs. 900 more, the profit would have be...
- The diagonals of a rhombus are in the ratio 7:5, and its area is 3,500 cm². A circle is formed taking the smaller diagonal as the diameter. Find the differ...
- Ravi and Kunal initiated a joint venture by contributing Rs. 6,000 and Rs. 7,200 respectively. After 6 months, Ravi boosted his investment by 30% and Kunal...
- Priya needs to travel from town 'X' to town 'Y'. If she drives at a steady speed of 60 km/h, she arrives 36 minutes early. However, if she drives at 40 km/...
- Determine the final value of this expression: (1/5) of {5⁴ - 24 × 14 + 12 × 18 - 10.5 of 10²}
- What is the length of the hypotenuse in an isosceles right-angled triangle if one of its equal sides measures 6√2 cm?
- A trader sold an article for Rs. 640 and made a profit of 28%. If he wants to increase his profit to 45%, what should be the new selling price?
- In 2021, Riya's income was Rs. 20000 out of which she spent 35% and saved the rest. In 2022, if Riya's income rose by 15% and her spending increased by Rs....
- The product of two numbers is 15.75. If one of the numbers is 4.5, then find the other number.
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)