Question
The standard time for a task is 4 hours per unit at a
wage rate of ₹60 per hour. In a period, 500 units were produced in 1,900 hours, and the actual wage rate was ₹65 per hour. What is the Labour Rate Variance?Solution
Labour Rate Variance = Actual Hours (AH) x (Standard Rate - Actual Rate). = 1,900 x (60 - 65) = 1,900 x (-5) = ₹9,500 Adverse (since actual rate paid is higher).
NDDB was established with the objective of taking up the activity of
Whiptail disease of cauliflower occurred due to the deficiency of which of the following nutrient?
Among the following, which one is the Arabica Coffee………………….
Fat content in double toned milk is ____
Demographic transition theory of population was proposed by
Largest share of horticultural crops in the fiscal year 2021?
This soil property which impacts nutrient movement to plant roots through mass flow and diffusion?
What principle ensures that extension activities aim for the satisfaction of the farmers and their families?
An institute at the State level for training of State department of agriculture people is
The total depth of water required by a crop is known as: