Question
A plant has one binding bottleneck: a heat-treating oven
(hours limited). Product P and Q both consume oven time; material is the only truly variable cost in the short run. P has higher gross margin per unit, but lower throughput per bottleneck hour than Q. Demand for both exceeds capacity; fixed costs are committed. Which production plan maximizes short-run profit?Solution
In throughput accounting with a single binding bottleneck, rank products by throughput per bottleneck hour (sales – truly variable costs per hour). With excess demand and fixed costs committed, prioritize Q if it yields higher throughput per constrained hour.
Select the set in which the numbers are related in the same way as are the numbers of the following set.
(13, 32, 21)
If all the letters in the word ‘CANTONMENT’ are arranged in alphabetical order from left to right such that the vowels are arranged first followed b...
45 : 9 ::Â (?) Â : 7
Select the option that is related to the third term in the same way as the second term is related to first term.
PURCHASING : RUPXSZHGNI:: REG...
Select the related number from the given alternatives.
42: 12:: 67: ?
If 5Ω9 = 90, 9Ω4 = 72 and 3Ω9 = 54, then find the value of 6Ω5 = ?
Change the question mark with the option that follows the logic applied to the first pair.Â
Television : Electricity :: Car : ??
Select the set of letters that when sequentially placed in the blanks of the given letter series will complete the series.
_ x y _ w _ y z w x _ _ w _ _ z
If 33 @ 16 = 15' and 41 @ 32 = 7', then 64 @ 33 = ?'. What will come in place of question mark?
If 21 @ 16 = 12 and 30 @ 25 = 12, then 22 @ 17 = ?'. What will come in place of question mark?