📢 Too many exams? Don’t know which one suits you best? Book Your Free Expert 👉 call Now!


    Question

    A plant has one binding bottleneck: a heat-treating oven

    (hours limited). Product P and Q both consume oven time; material is the only truly variable cost in the short run. P has higher gross margin per unit, but lower throughput per bottleneck hour than Q. Demand for both exceeds capacity; fixed costs are committed. Which production plan maximizes short-run profit?
    A Prioritize P because its unit margin is higher. Correct Answer Incorrect Answer
    B Prioritize Q because throughput per bottleneck hour is higher. Correct Answer Incorrect Answer
    C Split capacity 50:50 to diversify risk. Correct Answer Incorrect Answer
    D Produce to equal contribution per unit of material. Correct Answer Incorrect Answer
    E Shift to the product with lower setup times regardless of throughput. Correct Answer Incorrect Answer

    Solution

    In throughput accounting with a single binding bottleneck, rank products by throughput per bottleneck hour (sales – truly variable costs per hour). With excess demand and fixed costs committed, prioritize Q if it yields higher throughput per constrained hour.

    Practice Next
    ask-question