Question

Standard hours for actual production = 5,000 hours; Actual hours worked = 5,500; Std rate per hour = ₹80. Calculate Labour Efficiency Variance.

A ₹60,000 A
B ₹45,000 A
C ₹40,000 F
D ₹50,000 A
E ₹60,000 F