📢 Too many exams? Don’t know which one suits you best? Book Your Free Expert 👉 call Now!

  • google app store apple app store

    • Question

      Project A has cash flows of ₹-10 lakh (initial),

      ₹3L, ₹4L, ₹5L over 3 years. Project B has the same initial investment but generates ₹6L, ₹4L, ₹2L. At 10% discount rate, which project has higher NPV, and which has higher IRR?
      A A has higher NPV, B has higher IRR Correct Answer Incorrect Answer
      B A has both higher NPV and IRR Correct Answer Incorrect Answer
      C B has higher NPV, A has higher IRR Correct Answer Incorrect Answer
      D Both projects have equal IRR Correct Answer Incorrect Answer

      Solution

      Project A gives rising cash flows → Higher NPV at 10% Project B has earlier cash flows → Higher IRR due to timing Hence, A is better in NPV, B in IRR

      Practice Next

      Relevant for Exams:

      ask-question